Major Construction Projects for 2012-2013

Major Construction Projects   County
     
100 Series Expansion    
Highway 103: Broad River to Port Joli, new alignment (Multiple Year Project)   Queens
     
Highway 104; Antigonish Phase 1, 1.9 km west of Exit 31A to 0.6 km west of Exit 34, (total 7.9 km) (Multiple Year Project)   Antigonish
     
Highway 104: Antigonish Phase 2, from Beech Hill Road to Taylor Road, 8 km (Multiple Year Project)   Antigonish
     
Highway 104; Twinning 1 km east of Pine Tree Road to 500 m east of Route 245 (Multiple Year Project)   Pictou
     
Highway 125; Twinning Sydney River (Kings Road) to Grand Lake Road (Multiple Year Project)   Cape Breton
     
Construction 100 Series    
Highway 104: Exit 23 interchange signalization   Pictou
     
Construction on Arterial and Collector    
Cabot Trail (Trunk 30): from 2010 construction joint near Meadows Road (south end) northerly to Meadows Road (north end) – 6 km   Victoria
     
Cabot Trail (Trunk 30): from Old Cabot Trail Road intersection northerly to La Pointe De Havre Road – 6.4 km   Inverness
     
Trunk 4: from 0.2 km west of Campbell's Bridge westerly to 0.2 km west of MacNab's Bridge – 6.1 km   Richmond