This consolidation is unofficial and is for reference only.  For the official version of the regulations, consult the original documents on file with the Office of the Registrar of Regulations, or refer to the Royal Gazette Part II.
Regulations are amended frequently.  Please check the list of Regulations by Act to see if there are any recent amendments to these regulations filed with our office that are not yet included in this consolidation.
Although every effort has been made to ensure the accuracy of this electronic version, the Office of the Registrar of Regulations assumes no responsibility for any discrepancies that may have resulted from reformatting.
This electronic version is copyright © 2024, Province of Nova Scotia, all rights reserved.  It is for your personal use and may not be copied for the purposes of resale in this or any other form.


Green Choice Program Regulations

made under Section 4BC of the

Electricity Act

S.N.S. 2004, c. 25

O.I.C. 2023-234 (effective August 29, 2023), N.S. Reg. 155/2023

amended to O.I.C. 2024-388 (effective October 22, 2024), N.S. Reg. 226/2024



Table of Contents


Please note: this table of contents is provided for convenience of reference and does not form part of the regulations.
Click here to go to the text of the regulations.

 

Interpretation

Citation

Definitions

Eligibility, Application, Application Process and Compliance Requirements for
Participants

Eligibility requirements for participants

Application intake window for participants

Application requirements for participants

Application process for participants

Maximum electricity consumption enrollment at time of participant’s application

Incomplete participant applications

Evaluation and deferral of participant applications

Minister’s decision on participant’s application

Aggregate nameplate capacity for Green Choice Program

Fees, costs and penalties of Green Choice Program

Procurement and Power Purchase Agreements

Procurement of renewable low-impact electricity and awarding of power purchase agreement

Term of power purchase agreement

Termination of power purchase agreement

Subscription in Green Choice Program

Terms and conditions of subscription

Assignment of subscription

Term of subscription

Amendment of subscription terms and conditions

Reallocation of subscribed electricity

Renewable Energy Certificates

Registration and retirement of renewable energy certificates

Reporting Requirements

Supplier reporting requirements

NSPI reporting requirements

Renewable Electricity Standards

Green Choice Program electricity and renewable electricity standards

Green Choice Program Review

Program review



 


Interpretation


Citation

1        These regulations may be cited as the Green Choice Program Regulations.


Definitions

2        (1)    Except as otherwise provided in these regulations, words and expressions used in these regulations have the same meaning as in the Act and the Renewable Electricity Regulations made under the Act.

 

          (2)    In these regulations,

 

“Act” means the Electricity Act;

 

“aggregate partnership” means a partnership consisting of separate public institutions whose combined subscribed electricity is at least 10 000 000 kWh annually;

 

“applicant” means a person, public institution, business or aggregate partnership applying to become a participant;

 

“application” means the documents, information and forms submitted by an applicant to apply to become a participant;

 

“bidder” means a company or corporate body that is bidding on a request for proposals for procurement of renewable low-impact electricity for the Green Choice Program;

 

“eligible electricity”, for the purposes of the Green Choice Program, means renewable low-impact electricity that is all of the following:

 

                              (i)      not already supplied to a customer under any other program under the Act that directly generates renewable electricity for customer accounts and NSPI service locations,

 

                              (ii)     not currently directly supplied under a procurement under Section 4B or 4BA of the Act;

 

“fixed administrative costs” means costs incurred by NSPI to administer the Green Choice Program, including costs the Minister considers administrative in nature and any costs associated with the following activities:

 

                              (i)      billing,

 

                              (ii)     amending the terms and conditions of a participant’s subscription in the Green Choice Program,

 

                              (iii)    reallocating subscribed electricity,

 

                              (iv)    filing and transferring a REC,

 

                              (v)     reporting and record keeping,

 

                              (vi)    assisting an applicant in submitting their application,

 

                              (vii)   verifying the application processes with the Minister;

 

“participant” means any entity that participates in the Green Choice Program, including each partner in an aggregate partnership;

 

“partner” means one of the separate public institutions in an aggregate partnership;

 

“public institution” means any of the following:

 

                              (i)      a registered charity for income tax purposes,

 

                              (ii)     a school authority,

 

                              (iii)    a public college,

 

                              (iv)    a university,

 

                              (v)     a hospital authority,

 

                              (vi)    a municipal, provincial or federal government, including a department, agency or Crown corporation that is part of a municipal, provincial or federal government,

 

                              (vii)   a Mi’kmaw band council or its wholly owned subsidiaries;

 

“renewable energy certificate” or “REC” means a document that provides proof that a participant owns the renewable attributes per MWh of renewable energy generated;

 

“social procurement” means the achievement of strategic social, environmental, economic and workforce development goals through the purchasing of goods and services;

 

“subscribed electricity” means renewable low-impact electricity contracted by a participant in and produced by a supplier to the Green Choice Program;

 

“supplier” means an independent power producer as defined in the Renewable Electricity Regulations made under the Act.


Eligibility, Application, Application Process and Compliance Requirements for Participants


Eligibility requirements for participants

3        To be an eligible participant in the Green Choice Program, an applicant must meet all of the following requirements:

 

                   (a)      be 1 of the following entities:

 

                              (i)      a single corporate or commercial customer with a minimum subscription volume of 10 000 000 kWh annually in electricity load over 1 or more electricity meters,

 

                              (ii)     a public institution or its departments, agencies or Crown corporations with a minimum subscription volume of 10 000 000 kWh annually in electricity load over 1 or more electricity meters,

 

                              (iii)    an aggregated partnership of 2 or more separate public institutions who have aggregated their electricity load to achieve a minimum aggregated subscription volume of 10 000 000 kWh annually in electricity load over 1 or more electricity meters,

 

                              (iv)    a partner in an aggregated partnership with an electricity load of no less than 1 000 000 kWh annually or that subscribes a minimum of 10 000 000 kWh per year in the Green Choice Program;

 

                   (b)     be in good standing with NSPI or a new NSPI customer with the documentation required by clause 5(f);

 

                   (c)      only subscribe eligible electricity that is wholly generated and delivered within the Province;

 

                   (d)     be a customer with a customer account wholly located in the Province within NSPI’s service territory.


Application intake window for participants

4        (1)    The Minister may open an intake window for applications from eligible participants when there is nameplate capacity available in the Green Choice Program.

 

          (2)    The start and end dates of the intake window for applications from eligible participants must be posted publicly for at least 20 business days prior to the start date of the intake window.

 

          (3)    The start and end dates of the intake window for applications from eligible participants must be determined by the Minister.

 

          (4)    No applications will be accepted after the end date of the intake window for applications from eligible participants.


Application requirements for participants

5        An applicant must include all of the following in an application under subsection 4BA(3) of the Act:

 

                   (a)      an application form

 

                              (i)      containing the name, address, e-mail address and telephone number of the applicant, and

 

                              (ii)     completed and signed by a person who has authority to sign on behalf of the applicant;

 

                   (b)     confirmation that the applicant meets all of the eligibility requirements described in Section 3;

 

                   (c)      a document that outlines the total electricity load and the participating customer accounts to be enrolled in the Green Choice Program;

 

                   (d)     a statement specifying all of the following:

 

                              (i)      the amount of eligible electricity in kilowatt hours intended to be enrolled in the Green Choice Program annually,

 

                              (ii)     the intended length of the term of enrollment in the Green Choice Program;

 

                   (e)      for an aggregate partnership, all of the following:

 

                              (i)      the names of all partners in the aggregate partnership,

 

                              (ii)     a statement designating one of the partners or a third party as the representative of the aggregate partnership,

 

                              (iii)    proof that the partners have entered into an aggregate partnership, in the form of a copy of a letter, an agreement or other written documentation,

 

                              (iv)    confirmation by each partner that they will subscribe for the same term in their participant agreement as the other partners in the aggregate partnership;

 

                   (f)      for an applicant that is a new customer of NSPI, all of the following:

 

                              (i)      a credit check, in the form described in the application,

 

                              (ii)     proof of anticipated energy use, in a form acceptable to the Minister;

 

                   (g)     any other documents, information or forms required by the Minister and described in the application.


Application process for participants

6        (1)    All applications must be submitted in the form or manner required by the Minister, which may include electronic submission through the Internet.

 

          (2)    An applicant may withdraw their application at any time prior to being accepted into the Green Choice Program.

 

          (3)    An applicant may apply for eligible electricity only.

 

          (4)    An applicant may apply to 1 or more application intake windows described in Section 4, if they are subscribing new eligible electricity.

 

          (5)    Applications from ineligible participants will be rejected.

 

          (6)    The Minister may contact NSPI to verify any of the information included in an application.


Maximum electricity consumption enrollment at time of participant’s application

7        Upon application, an applicant may enroll up to a maximum of 120% of their electricity consumption, as calculated by the Green Choice Program based on the applicant’s electricity consumption during the previous year or years selected by the Green Choice Program, unless otherwise approved by the Minister.


Incomplete participant applications

8        Incomplete applications must be rejected, including applications containing information that cannot be verified.


Evaluation and deferral of participant applications

9        (1)    The Minister may consider all of the following when evaluating applications from eligible participants:

 

                   (a)      whether an eligible participant has made a public climate change or emissions reduction commitment;

 

                   (b)     the date by which an eligible participant must meet the climate change or emissions reduction commitment described in clause (a);

 

                   (c)      the total aggregate nameplate capacity available under the Green Choice Program;

 

                   (d)     for an eligible participant that is a new NSPI customer, the long-term economic viability of the eligible participant and the accuracy of the energy modelling for the eligible participant’s new NSPI service locations;

 

                   (e)      any other information the Minister deems appropriate.

 

          (2)    The Minister has the discretion to determine the total number of eligible participants and the total amount of subscribed electricity enrolled in the Green Choice Program.

 

          (3)    If an eligible participant submits a complete application, but is not selected to participate in the Green Choice Program, the Minister may defer the eligible participant’s acceptance and hold their application on file for up to 3 years.

 

          (4)    If capacity becomes available within the Green Choice Program during the 3-year period referred to in subsection (3), the Minister may select a deferred eligible participant to participate in the Green Choice Program and enrol the eligible participant’s requested amount of subscribed electricity in the Green Choice Program with the eligible participant’s consent.


Minister’s decision on participant’s application

10      (1)    The Minister must, no later than 45 business days after the close of the intake window for applications from eligible participants, provide written notification to an eligible participant that their application has been accepted, deferred or rejected.

 

          (2)    Before accepting, deferring or rejecting an application, the Minister may request additional information from an eligible participant to clarify the information submitted in their application.

 

          (3)    All additional information requested by the Minister under subsection (2) must be submitted within a time frame specified by the Minister.

 

          (4)    If the additional information requested under subsection (2) is not received within the time frame specified by the Minister, the Minister may deem the application incomplete and reject it.

 

          (5)    The Minister must notify NSPI of all eligible participants accepted into the Green Choice Program and all eligible participants deferred.


Aggregate nameplate capacity for Green Choice Program

11      The aggregate nameplate capacity of all NSPI service locations accepted into the Green Choice Program must not exceed 1 500 000 000 kWh.


Fees, costs and penalties of Green Choice Program

12      (1)    Participants must incur no fees, costs or penalties associated with the Green Choice Program outside of those listed in these regulations.

 

          (2)    A fixed administrative cost charged under these regulations must not exceed $0.001 per kWh of eligible subscribed electricity contracted by the participant, up to a total of $100 000 per participant annually.

 

          (3)    A participant who is charged a fixed administrative cost by NSPI under these regulations or who receives a credit under subsection 4BB(2) of the Act must receive a billing adjustment that consists of two separate line items on the participant’s bill.


Procurement and Power Purchase Agreements


Procurement of renewable low-impact electricity and awarding of power purchase agreement

13      (1)    Procurement of renewable low-impact electricity must comply with Section 4B of the Act and Sections 35A, 35B, 35C, 35D, 36 and 37 of the Renewable Electricity Regulations made under the Act.

 

          (2)    If a procurement administrator awards a power purchase agreement to a successful bidder, the bidder’s renewable electricity projects become the renewable energy suppliers for the participants’ subscribed electricity for the purpose of the Green Choice Program.


Term of power purchase agreement

14      A power purchase agreement must be for a term of 25 years starting from the commercial operation date.


Termination of power purchase agreement

15      If a power purchase agreement issued under the Green Choice Program is terminated, NSPI must provide notification of the termination in writing to the Board and the Minister within 30 business days.


Subscription in Green Choice Program


Terms and conditions of subscription

16      (1)    NSPI must, in collaboration with the participants, update the participants’ subscriptions no later than 90 business days before the commercial operation dates of the suppliers specified in the power purchase agreements.

 

          (2)    A participant must confirm the term of their subscription in the Green Choice Program, as defined in the terms and conditions of the participant’s subscription, in accordance with Section 18.

 

          (3)    A participant may terminate their subscription in the Green Choice Program before the end of their subscription term, as defined in the terms and conditions of the participant’s subscription, if they provide 90 days’ written notice of the termination to NSPI and the Minister.

 

          (4)    A participant may be charged costs and receive credits when

 

                   (a)      the first supplier in the Green Choice Program begins commercial operation, as defined in the supplier’s power purchase agreement; and

 

                   (b)     the participant receives renewable low-impact electricity from the first supplier in the Green Choice Program to begin commercial operation.

 

          (5)    NSPI must notify the participants and the Minister of when all of the following will occur at least 7 business days before they occur:

 

                   (a)      a supplier project achieves commercial operation;

 

                   (b)     the terms and conditions of the participants’ subscriptions in the Green Choice Program come into effect;

 

                   (c)      costs and credits begin to be charged, for billing purposes.


Assignment of subscription

17      (1)    A participant may assign or transfer their subscription in the Green Choice Program to a subsidiary, affiliated party, Crown corporation, department or agency of a public institution if the assignee or transferee accepts the same terms and conditions of the subscription as the participant.

 

          (2)    An assignment of a participant’s subscription is subject to approval by NSPI and that approval must not be unreasonably withheld.

 

          (3)    A participant must notify the Minister in writing when the participant’s subscription has been transferred or assigned.

 

          (4)    A participant must submit to NSPI, on behalf of the assignee to whom the participant has assigned their subscription, documents that demonstrate all of the following:

 

                   (a)      that the results of the credit check of the assignee are equal to or greater than those of the participant at the time of the assignment;

 

                   (b)     that the assignee has acquired an interest in the NSPI service locations or locations associated with the participant’s subscribed electricity.


Term of subscription

18      (1)    A participant must subscribe to the Green Choice Program for a minimum of 5 years.

 

          (2)    A participant may extend the term of their subscription every 5 years.

 

          (3)    A participant must provide 90 business days’ written notice to NSPI and the Minister of their intention to extend their subscription term.

 

          (4)    The maximum amalgamated term of a participant’s subscription must not exceed 25 years.


Amendment of subscription terms and conditions

19      The terms and conditions of a participant’s subscription in the Green Choice Program may be amended by NSPI or the participant, subject to the approval of both the participant and NSPI.


Reallocation of subscribed electricity

20      (1)    If a participant or aggregate partnership has decreased their subscribed electricity or a participant has not extended or terminated their subscription, NSPI must make a reasonable effort to reallocate and reassign the newly available subscribed electricity among the remaining participants by

 

                   (a)      notifying the remaining participants of the availability of the subscribed electricity; and

 

                   (b)     allowing the remaining participants to request an increase in their subscribed electricity.

 

          (2)    If NSPI cannot, within 60 business days, reallocate or reassign the subscribed electricity described in subsection (1) to the remaining participants, NSPI must notify the Minister of the amount of available electricity supply under the Green Choice Program.

 

          (3)    Upon receipt of a notification from NSPI provided under subsection (2), the Minister may do any of the following:

 

                   (a)      open a new application intake window;

 

                   (b)     if it has been less than 3 years since the end of the previous application intake window, contact deferred eligible participants.

 

          (4)    If 365 calendar days have elapsed since NSPI notified the Minister under subsection (2) and the subscribed electricity has not been allocated to new participants, it may be allocated to serve the general ratepayer, in which case the subscribed electricity will no longer be available for subscription under the Green Choice Program.


Renewable Energy Certificates


Registration and retirement of renewable energy certificates

21      (1)    NSPI must register annually, on behalf of a participant, a renewable energy certificate with an internationally recognized organization.

 

          (2)    Each year on or before September 30, NSPI must provide the participant with all of the following information about the renewable energy certificate registration:

 

                   (a)      annual volume of the participant’s renewable energy certificate;

 

                   (b)     the participant’s identification numbers;

 

                   (c)      vintage.

 

          (3)    Upon NSPI providing the participant with the specifics of the renewable energy certificate registration under subsection (2), the renewable energy certificate will be considered retired.


Reporting Requirements


Supplier reporting requirements

22      (1)    The Minister may request reports from a supplier, as required, regarding all of the following:

 

                   (a)      the supplier’s progress in putting its electricity generation facility into service, if the electricity generation facility has not reached commercial operation;

 

                   (b)     social procurement activities and local economic benefits, including employment, instigated by the supplier in the previous year and plans for any social procurement activities and local economic benefits in the upcoming year;

 

                   (c)      technical data, upon the commencement of the commercial operation of a electricity generation facility.

 

          (2)    The Minister may specify the form and content of supplier reports requested under subsection (1).

 

          (3)    The Minister may publish aggregate information from supplier reports submitted in response to requests made under subsection (1).


NSPI reporting requirements

23      On or before January 31 of each year, NSPI must provide a report to the Minister and the Board summarizing all of the following actions taken in the previous calendar year regarding the participants and power purchase agreements that are under the Green Choice Program:

 

                   (a)      any extension, assignment, transfer or termination of a subscription of a participant;

 

                   (b)     any transfer, assignment or termination of a power purchase agreement.


Renewable Electricity Standards


Green Choice Program electricity and renewable electricity standards

24      All electricity procured under the Green Choice Program may be used by NSPI to meet the renewable electricity standards.


Green Choice Program Review


Program review

25      The Minister may review the Green Choice Program, including any associated costs, fees and benefits, as needed, but must do so no later than December 31, 2030.


 

 


 

Legislative History
Reference Tables

Green Choice Program Regulations

N.S. Reg. 155/2023

Electricity Act

Note:  The information in these tables does not form part of the regulations and is compiled by the Office of the Registrar of Regulations for reference only.

Source Law

The current consolidation of the Green Choice Program Regulations made under the Electricity Act includes all of the following regulations:

N.S.
Regulation

In force
date*

How in force

Royal Gazette
Part II Issue

155/2023

Aug 29, 2023

date specified

Sep 8, 2023

226/2024

Oct 22, 2024

date specified

Nov 1, 2024

 

 

 

 

 

 

 

 

 

 

 

 

The following regulations are not yet in force and are not included in the current consolidation:

N.S.
Regulation

In force
date*

How in force

Royal Gazette
Part II Issue

 

 

 

 

 

 

 

 

 

 

 

 

*See subsection 3(6) of the Regulations Act for rules about in force dates of regulations.

Amendments by Provision

ad. = added
am. = amended

fc. = fee change
ra. = reassigned

rep. = repealed
rs. = repealed and substituted

Provision affected

How affected

2(2), defn. of “aggregate partnership”........................................................

am. 226/2024

2(2), defn. of “eligible electricity”...

am. 226/2024

2(2), defn. of “subscribed electricity”

am. 226/2024

3(a)(i)-(iv).........................................

am. 226/2024

5(d)(i)...............................................

am. 226/2024

9(1)(d)...............................................

am. 226/2024

11......................................................

am. 226/2024

12(2).................................................

am. 226/2024

12(3).................................................

ad. 226/2024

16(1).................................................

am. 226/2024

16(4).................................................

rs. 226/2024

17(4)(b).............................................

am. 226/2024

20(1)(b).............................................

am. 226/2024

21......................................................

am. 226/2024

25......................................................

am. 226/2024

Note that changes to headings are not included in the above table.

Editorial Notes and Corrections

 

Note

Effective
date

 

 

 

 

 

 

 

 

 

Repealed and Superseded

N.S.
Regulation

Title

In force
date

Repealed
date

 

 

 

 

Note:  Only regulations that are specifically repealed and replaced appear in this table.  It may not reflect the entire history of regulations on this subject matter.

 